SR. NO. | NAME OF APPROVAL | NAME OF DEPARTMENT | TIMELINE | DOCUMENT REQUIRED | CONTACT DETAILS OF NODAL |
---|---|---|---|---|---|
1 | NOC from Fire Department (Provisional N.O.C for Occupation of Building over 15 metres in height from the ground) | Directorate of Fire and Emergency Services | 15 days | 1.One set of blue print (approved by Planning & Development Authority) of the site plan, Elevations, Section and all floor plans signed by the owner and Architect/Engineer. 2.One set of Fire Protection Plans signed by the Owner and Architect/Consultant indicating the Fire Prevention and Fire Protection Provisions (Active & passive) that are proposed to be incorporated in the building 3.Declaration of the Architect and Owners of the building in the format provided by the Directorate (specimen attached as Annexure ‘A’) 4.An undertaking signed by the Owner/Applicant on a Rs.50/- Stamp Paper for abiding with the fire prevention and fire protection measures as required in the initial NO Objection Certificate or as amended from time to time (specimen attached as Annexure ‘B’) | Shri. Nitin Raiker dir[hyphen]fire[dot]goa[at]nic[dot]in |
2 | NOC from Fire Department (Provisional N.O.C for Factories and Establishments where electrical motor capacity exceeds 5 H.P and above) | Directorate of Fire and Emergency Services | 15 days | 1.One set of blue print (approved by Planning & Development Authority) of the site plan, Elevations, Section and all floor plans signed by the owner and Architect/Engineer. 2.One set of Fire Protection Plans signed by the Owner and Architect/Consultant indicating the Fire Prevention and Fire Protection Provisions (Active & passive) that are proposed to be incorporated in the building 3.Declaration of the Architect and Owners of the building in the format provided by the Directorate (specimen attached as Annexure ‘A’) 4.An undertaking signed by the Owner/Applicant on a Rs.50/- Stamp Paper for abiding with the fire prevention and fire protection measures as required in the initial NO Objection Certificate or as amended from time to time (specimen attached as Annexure ‘B’) | Shri. Nitin Raiker dir[hyphen]fire[dot]goa[at]nic[dot]in |
3 | NOC from Fire Department (Provisional N.O.C for Shipyards and Workshops) | Directorate of Fire and Emergency Services | 15 days | 1.One set of blue print (approved by Planning & Development Authority) of the site plan, Elevations, Section and all floor plans signed by the owner and Architect/Engineer. 2.One set of Fire Protection Plans signed by the Owner and Architect/Consultant indicating the Fire Prevention and Fire Protection Provisions (Active & passive) that are proposed to be incorporated in the building 3.Declaration of the Architect and Owners of the building in the format provided by the Directorate (specimen attached as Annexure ‘A’) 4.An undertaking signed by the Owner/Applicant on a Rs.50/- Stamp Paper for abiding with the fire prevention and fire protection measures as required in the initial NO Objection Certificate or as amended from time to time (specimen attached as Annexure ‘B’) | Shri. Nitin Raiker dir[hyphen]fire[dot]goa[at]nic[dot]in |
4 | NOC from Fire Department (Provisional N.O.C for Tank Farm of Petroleum Products) | Directorate of Fire and Emergency Services | 15 days | 1.One set of blue print (approved by Planning & Development Authority) of the site plan, Elevations, Section and all floor plans signed by the owner and Architect/Engineer. 2.One set of Fire Protection Plans signed by the Owner and Architect/Consultant indicating the Fire Prevention and Fire Protection Provisions (Active & passive) that are proposed to be incorporated in the building 3.Declaration of the Architect and Owners of the building in the format provided by the Directorate (specimen attached as Annexure ‘A’) 4.An undertaking signed by the Owner/Applicant on a Rs.50/- Stamp Paper for abiding with the fire prevention and fire protection measures as required in the initial NO Objection Certificate or as amended from time to time (specimen attached as Annexure ‘B’) | Shri. Nitin Raiker dir[hyphen]fire[dot]goa[at]nic[dot]in |
5 | NOC from Fire Department (Provisional N.O.C for POL dispensing outlet) | Directorate of Fire and Emergency Services | 15 days | 1.One set of blue print (approved by Planning & Development Authority) of the site plan, Elevations, Section and all floor plans signed by the owner and Architect/Engineer. 2.One set of Fire Protection Plans signed by the Owner and Architect/Consultant indicating the Fire Prevention and Fire Protection Provisions (Active & passive) that are proposed to be incorporated in the building 3.Declaration of the Architect and Owners of the building in the format provided by the Directorate (specimen attached as Annexure ‘A’) 4.An undertaking signed by the Owner/Applicant on a Rs.50/- Stamp Paper for abiding with the fire prevention and fire protection measures as required in the initial NO Objection Certificate or as amended from time to time (specimen attached as Annexure ‘B’) | Shri. Nitin Raiker dir[hyphen]fire[dot]goa[at]nic[dot]in |
6 | NOC from Fire Department (Provisional N.O.C for Godown and Warehouses (High Hazard) | Directorate of Fire and Emergency Services | 15 days | 1.One set of blue print (approved by Planning & Development Authority) of the site plan, Elevations, Section and all floor plans signed by the owner and Architect/Engineer. 2.One set of Fire Protection Plans signed by the Owner and Architect/Consultant indicating the Fire Prevention and Fire Protection Provisions (Active & passive) that are proposed to be incorporated in the building 3.Declaration of the Architect and Owners of the building in the format provided by the Directorate (specimen attached as Annexure ‘A’) 4.An undertaking signed by the Owner/Applicant on a Rs.50/- Stamp Paper for abiding with the fire prevention and fire protection measures as required in the initial NO Objection Certificate or as amended from time to time (specimen attached as Annexure ‘B’) | Shri. Nitin Raiker dir[hyphen]fire[dot]goa[at]nic[dot]in |
7 | NOC from Fire Department (Provisional N.O.C for Godown and Warehouses (Moderate Hazard) | Directorate of Fire and Emergency Services | 15 days | 1.One set of blue print (approved by Planning & Development Authority) of the site plan, Elevations, Section and all floor plans signed by the owner and Architect/Engineer. 2.One set of Fire Protection Plans signed by the Owner and Architect/Consultant indicating the Fire Prevention and Fire Protection Provisions (Active & passive) that are proposed to be incorporated in the building 3.Declaration of the Architect and Owners of the building in the format provided by the Directorate (specimen attached as Annexure ‘A’) 4.An undertaking signed by the Owner/Applicant on a Rs.50/- Stamp Paper for abiding with the fire prevention and fire protection measures as required in the initial NO Objection Certificate or as amended from time to time (specimen attached as Annexure ‘B’) | Shri. Nitin Raiker dir[hyphen]fire[dot]goa[at]nic[dot]in |
8 | NOC from Fire Department (Provisional N.O.C for Godown and Warehouses (Low Hazard) | Directorate of Fire and Emergency Services | 15 days | 1.One set of blue print (approved by Planning & Development Authority) of the site plan, Elevations, Section and all floor plans signed by the owner and Architect/Engineer. 2.One set of Fire Protection Plans signed by the Owner and Architect/Consultant indicating the Fire Prevention and Fire Protection Provisions (Active & passive) that are proposed to be incorporated in the building 3.Declaration of the Architect and Owners of the building in the format provided by the Directorate (specimen attached as Annexure ‘A’) 4.An undertaking signed by the Owner/Applicant on a Rs.50/- Stamp Paper for abiding with the fire prevention and fire protection measures as required in the initial NO Objection Certificate or as amended from time to time (specimen attached as Annexure ‘B’) | Shri. Nitin Raiker dir[hyphen]fire[dot]goa[at]nic[dot]in |
9 | NOC from Fire Department (Provisional N.O.C for public places like exhibition halls, entertainment places, dancing halls, theatres, assembly halls, seaport, airport, railway station, bus stations, stadium) | Directorate of Fire and Emergency Services | 15 days | 1.One set of blue print (approved by Planning & Development Authority) of the site plan, Elevations, Section and all floor plans signed by the owner and Architect/Engineer. 2.One set of Fire Protection Plans signed by the Owner and Architect/Consultant indicating the Fire Prevention and Fire Protection Provisions (Active & passive) that are proposed to be incorporated in the building 3.Declaration of the Architect and Owners of the building in the format provided by the Directorate (specimen attached as Annexure ‘A’) 4.An undertaking signed by the Owner/Applicant on a Rs.50/- Stamp Paper for abiding with the fire prevention and fire protection measures as required in the initial NO Objection Certificate or as amended from time to time (specimen attached as Annexure ‘B’) | Shri. Nitin Raiker dir[hyphen]fire[dot]goa[at]nic[dot]in |
10 | NOC from Fire Department (Provisional N.O.C for Educational and Institutional Places) | Directorate of Fire and Emergency Services | 15 days | 1.One set of blue print (approved by Planning & Development Authority) of the site plan, Elevations, Section and all floor plans signed by the owner and Architect/Engineer. 2.One set of Fire Protection Plans signed by the Owner and Architect/Consultant indicating the Fire Prevention and Fire Protection Provisions (Active & passive) that are proposed to be incorporated in the building 3.Declaration of the Architect and Owners of the building in the format provided by the Directorate (specimen attached as Annexure ‘A’) 4.An undertaking signed by the Owner/Applicant on a Rs.50/- Stamp Paper for abiding with the fire prevention and fire protection measures as required in the initial NO Objection Certificate or as amended from time to time (specimen attached as Annexure ‘B’) | Shri. Nitin Raiker dir[hyphen]fire[dot]goa[at]nic[dot]in |
11 | NOC from Fire Department (Provisional N.O.C for Steam Engines and Boilers to construct or establish any factory workshop or workplace in which it is proposed to employ steam power , water power or other mechanical power or electrical power) | Directorate of Fire and Emergency Services | 10 days | 1.One set of blue print (approved by Planning & Development Authority) of the site plan, Elevations, Section and all floor plans signed by the owner and Architect/Engineer. 2.One set of Fire Protection Plans signed by the Owner and Architect/Consultant indicating the Fire Prevention and Fire Protection Provisions (Active & passive) that are proposed to be incorporated in the building 3.Declaration of the Architect and Owners of the building in the format provided by the Directorate (specimen attached as Annexure ‘A’) 4.An undertaking signed by the Owner/Applicant on a Rs.50/- Stamp Paper for abiding with the fire prevention and fire protection measures as required in the initial NO Objection Certificate or as amended from time to time (specimen attached as Annexure ‘B’) | Shri. Nitin Raiker dir[hyphen]fire[dot]goa[at]nic[dot]in |
12 | NOC from Fire Department (Provisional NOC for storage places of flammable and hazardous goods.) | Directorate of Fire and Emergency Services | 10 days | 1.One set of blue print (approved by Planning & Development Authority) of the site plan, Elevations, Section and all floor plans signed by the owner and Architect/Engineer. 2.One set of Fire Protection Plans signed by the Owner and Architect/Consultant indicating the Fire Prevention and Fire Protection Provisions (Active & passive) that are proposed to be incorporated in the building 3.Declaration of the Architect and Owners of the building in the format provided by the Directorate (specimen attached as Annexure ‘A’) 4.An undertaking signed by the Owner/Applicant on a Rs.50/- Stamp Paper for abiding with the fire prevention and fire protection measures as required in the initial NO Objection Certificate or as amended from time to time (specimen attached as Annexure ‘B’) | Shri. Nitin Raiker dir[hyphen]fire[dot]goa[at]nic[dot]in |
13 | NOC from Fire Department (Provisional NOC for Hotel under 3 & 4 starred Category as per National Building Code of India 2005, Part 4 (Fire and Life Safety) | Directorate of Fire and Emergency Services | 10 days | 1.One set of blue print (approved by Planning & Development Authority) of the site plan, Elevations, Section and all floor plans signed by the owner and Architect/Engineer. 2.One set of Fire Protection Plans signed by the Owner and Architect/Consultant indicating the Fire Prevention and Fire Protection Provisions (Active & passive) that are proposed to be incorporated in the building 3.Declaration of the Architect and Owners of the building in the format provided by the Directorate (specimen attached as Annexure ‘A’) 4.An undertaking signed by the Owner/Applicant on a Rs.50/- Stamp Paper for abiding with the fire prevention and fire protection measures as required in the initial NO Objection Certificate or as amended from time to time (specimen attached as Annexure ‘B’) | Shri. Nitin Raiker dir[hyphen]fire[dot]goa[at]nic[dot]in |
14 | NOC from Fire Department (Provisional NOC for Storing and/or selling of Fire Works more than 25 kgs. And up to 50 Kgs. under Explosive Act 1984 and Rules 1983) | Directorate of Fire and Emergency Services | 10 days | 1.One set of blue print (approved by Planning & Development Authority) of the site plan, Elevations, Section and all floor plans signed by the owner and Architect/Engineer. 2.One set of Fire Protection Plans signed by the Owner and Architect/Consultant indicating the Fire Prevention and Fire Protection Provisions (Active & passive) that are proposed to be incorporated in the building 3.Declaration of the Architect and Owners of the building in the format provided by the Directorate (specimen attached as Annexure ‘A’) 4.An undertaking signed by the Owner/Applicant on a Rs.50/- Stamp Paper for abiding with the fire prevention and fire protection measures as required in the initial NO Objection Certificate or as amended from time to time (specimen attached as Annexure ‘B’) | Shri. Nitin Raiker dir[hyphen]fire[dot]goa[at]nic[dot]in |
15 | NOC from Fire Department (Provisional NOC for Storing and/or selling of Fire Works upto 25 kgs. Under Explosive Act 1984 and Rules, 1983) | Directorate of Fire and Emergency Services | 10 days | 1.One set of blue print (approved by Planning & Development Authority) of the site plan, Elevations, Section and all floor plans signed by the owner and Architect/Engineer. 2.One set of Fire Protection Plans signed by the Owner and Architect/Consultant indicating the Fire Prevention and Fire Protection Provisions (Active & passive) that are proposed to be incorporated in the building 3.Declaration of the Architect and Owners of the building in the format provided by the Directorate (specimen attached as Annexure ‘A’) 4.An undertaking signed by the Owner/Applicant on a Rs.50/- Stamp Paper for abiding with the fire prevention and fire protection measures as required in the initial NO Objection Certificate or as amended from time to time (specimen attached as Annexure ‘B’) | Shri. Nitin Raiker dir[hyphen]fire[dot]goa[at]nic[dot]in |
16 | Water Connection outside of Industrial Areas (New Water Connection) | Public Works Department | 30 Days | 1.Affidavit(on Rs 50/- stamp paper) 2.Plumber Certificate 3.Site Plan 4.Plumbing layout 5.Form I & XIV/Form D/Sale Deed(Ownership Document) 6.Neighbour's water bill(latest) 7.Identity Proof(Aadhaar/Epic) 8.NOC from Panchayat/CCP/Health Act Order 9.Latest House Tax paid Receipt(In case of Domestic Connections) 10.Occupancy Certificate(In case of New Premises) 11.Floor wise plan 12.Power of Attorny(In case of Rented Premises) 13.Trade License(In case of Non-Domestic) | Shri Santosh B Ce1[hyphen]pwd[dot]goa[at]nic[dot]in |
17 | Road Cutting Permission (Right of Way) | Public Works Department | 45 Days | 1. Form I & XIV. 2. Site Plan. 3. NOC from land owner(In case of watre connection pipeline crosses others property) | Shri Santosh B Ce1[hyphen]pwd[dot]goa[at]nic[dot]in |
18 | Sewerage Connection (New Sewerage Connection) | Public Works Department | 30 Days | - | Shri Santosh B Ce1[hyphen]pwd[dot]goa[at]nic[dot]in |
19 | Consent to Establish | Goa State Pollution Control Board | 45 Days (Green Category) 60 Days (Orange Category) 90 Days (Red Category) | 1. Land Allotment/earmarking letter or lease/Sale deed/Form I & XIV. 2. Flow Chart and detailed production process. 3. A copy of Project Report for projects costing Five crores and above. 4. Site plan (not required for units to be set up in Industrial Estates.) 5. Layout plan showing the location of manufacturing equipments, water supply/drainage lines,position of chimneys, effluent treatment plant and final discharge Point, Sludge solid waste disposal points and septic tanks/soak pits. 6. For industries/activities listed in Schedule I of the Environmental Impact Assessment (EIA) Notification 2006 copy of the EIA report/Form/Report submitted for obtaining Environmental Clearance and other survey, if required will have to be furnished in the prescribed time limit. 7. Photocopy of the prior Environmental Clearance (EC) issued by the Competent Authority, if applicable, for project listed in the Environment Impact Assessment (EIA) Notification, 2006,as amended from time to time. 8. Site plan showing surrounding Residential area, public places, water stream, etc., of the factory site within a radius of 5kms with waste water treatment and disposal systems clearly indicating where waste ² water is proposed to be disposed off (for medium and large scale enterprises). 9. Schematic sketch of the proposed effluent/sewage treatment system/plant (ETP/STP) and/or septic tanks/soak pit, duly signed by authorized person, along with detailed design calculation. 10. Certificate from Chartered Accountant certifying the Total Estimated Investment (T.E.I). (refer sample specimen below). In case of leased/hired premises/plant/machinery/equipment a certificate from a Registered Valuer towards capital cost is to be submitted without appreciation and depreciation. 11. Original authorization letter of the person to whom authorization is made to sign this application form except individual proprietary concern. 12. Any other documents/clarification as requisition by the Goa State Pollution Control Board. | Shri Nandan Prabhudessai nandan[dot]prabhudessai[dot]np[at]gmail[dot]com |
20 | Renewal of Consent to Establish | Goa State Pollution Control Board | 45 Days (Green Category) 60 Days (Orange Category) 90 Days (Red Category) | - | Shri Nandan Prabhudessai nandan[dot]prabhudessai[dot]np[at]gmail[dot]com |
21 | Tree Felling | Forest Department | To Be Defined | - | Shri Anand Jadhav Dcfhq[hyphen]forest[dot]goa[at]nic[dot]in |
22 | Tree Transit | Forest Department | To Be Defined | - | Shri Anand Jadhav Dcfhq[hyphen]forest[dot]goa[at]nic[dot]in |
23 | Licence for Establishment of Distillery / Brewery / Winery | Excise Department | No timeline prescribed | - | Smt. Shilpa Gawas gawasshilpa[dot]goa[at]gov[dot]in |
24 | Registration to set up Solar/ Renewal Energy Power Project | Goa Energy Development Agency (GEDA) | No timeline prescribed | - | - |
25 | Plot allotment in Industrial Estates and its possession | Goa Industrial Development Corporation | Fixing of meeting of Screening Committee - Within 30 days from the last date of application Communication of the decision about the offer of allotment of plot - 30 days from the date of receipt of report of Screening Committee Confirmation/Allotment order to the Party - 30 days from the date of applicant’s deposited payment Physical possession - 30 days from the date of allotment of order Issue of Draft of Lease Deed - 30 days from the date of allotment of order | - | Shri P. Pravimal Abhishek goaidc1965[at]gmail[dot]com |
26 | Application for Amalgamation permission prior to construction in industrial Estates (if required) | Goa Industrial Development Corporation | No timeline prescribed | - | Shri P. Pravimal Abhishek goaidc1965[at]gmail[dot]com |
27 | Permission to develop the land prior to construction / Building Plan Approval in Industrial Estates | Goa Industrial Development Corporation | No timeline prescribed | - | Shri P. Pravimal Abhishek goaidc1965[at]gmail[dot]com |
28 | Application for obtaining construction permit in Industrial Estates | Goa Industrial Development Corporation | 30 Days | - | Shri P. Pravimal Abhishek goaidc1965[at]gmail[dot]com |
29 | Application for plinth inspection | Goa Industrial Development Corporation | 7 Days | - | Shri P. Pravimal Abhishek goaidc1965[at]gmail[dot]com |
30 | NOC for Water connection in industrial area | Goa Industrial Development Corporation | No timeline prescribed | - | Shri P. Pravimal Abhishek goaidc1965[at]gmail[dot]com |
31 | Approval of factory plans | Inspectorate of Factories & Boilers | 90 Days | - | Shri. Premanand V. Gaude pgaude[hyphen]ifb[dot]goa[at]nic[dot]in |
32 | Registration of Boiler | Inspectorate of Factories & Boilers | 30 Days | 1.Copies of Boiler Drawing certificate issued by Boiler Manufacturer 2.Inspection clearance Certificate issued by competent person 3.Paid e-challan / receipt in original towards payment of fees. 4.Final folder of the Boiler issued by the Inspecting / Competent Authority of the State where it is manufactured. | Shri. Premanand V. Gaude pgaude[hyphen]ifb[dot]goa[at]nic[dot]in |
33 | Grant of License for Construction of any Structure | Panchayat Directorate | 30 Days | - | Smt. Siddhi Halarnakar dir[hyphen]panc[dot]goa[at]nic[dot]in |
34 | Issue of Development permission under Section 44 of the Town & Country Planning Act (i) Various buildings (ii) .Agro Based Activity/Industry, (iii) Industry outside Industrial Estate, Hotel/Resorts, Multi-storey (high rise) Building, Agricultural purposes & ancillaries (iv) IT Industries (v) Sub-division of Land | Planning & Development Authority (PDA) | 30 Days | - | - |
35 | Permission Under 17-A of the Town & Country Planning Act | Planning & Development Authority (PDA) | 30 Days | - | - |
36 | No Objection Certificate under Section 49 (6) of the Town & Country Planning Act | Planning & Development Authority (PDA) | 21 Days | - | - |
37 | Issue of Zoning information/certificate | Planning & Development Authority (PDA) | 10 Days | - | - |
38 | Conversion of Land u/s 32 of the Land Revenue Code | Revenue Department | 63 days from application | 1.Form I & XIV. 2. Survey plan. 3. One Notarized copy of Sale Deed etc. 4. Site plan on the basis of survey plan. 5. Zonning Certificate. | Shri. Surendra Naik jsrev[hyphen]sect[dot]goa[at]gov[dot]in |
39 | Issue of Technical Clearances for (i) Various buildings (ii) .Agro Based Activity/Industry, (iii) Industry outside Industrial Estate, Hotel/Resorts, Multi-storey (high rise) Building, Agricultural purposes & ancillaries (iv) IT Industries (v) Sub-division of Land | Town & Country Planning Department (TCP Dept.) | 30 Days | - | Smt. Vertika Dagur vertika[dot]dagur[at]gov[dot]in |
40 | Permission Under 17-A of the Town & Country Planning Act | Town & Country Planning Department (TCP Dept.) | 30 Days | - | Smt. Vertika Dagur vertika[dot]dagur[at]gov[dot]in |
41 | Issue of Site plans/layout plans | Goa Industrial Development Corporation | 5 Days | - | Shri P. Pravimal Abhishek goaidc1965[at]gmail[dot]com |
42 | Construction in CRZ | Goa Coastal Zone Management Authority | No timeline prescribed | - | - |
43 | Repairs on construction in CRZ (Modification) | Goa Coastal Zone Management Authority | No timeline prescribed | - | - |
44 | Construction License | Directorate of Municipal Administration | 19 Days | - | Shri Gurudas Pilarnekar dir[hyphen]dma[dot]goa[at]nic[dot]in |